UVA Health Culpeper Medical Center Renovations

Scope of Services
Mechanical, Electrical, Plumbing, and Fire Protection (MEP/FP) Engineering
 

Culpeper Medical Center is a community hospital offering a range of specialty services including orthopedics, cardiology, and cancer care. Following its acquisition by UVA Health, the organization initiated a multi-phase improvement plan to address critical infrastructure needs, enhance the patient experience, and support expanding services across the campus.

2RW Project Case Study Main Image
Services

2RW provided mechanical, electrical, plumbing, and fire protection (MEP/FP) engineering for several key renovations within the hospital and an adjacent clinical building. These included the interior fit-outs of the cancer center’s infusion bays and isolation area, a new pre-op unit, and an updated café to better serve patients, staff, and visitors. In the adjacent building, 2RW supported the renovation of a new OBGYN clinic, transforming the space to accommodate clinical functions for women’s health. We also upgraded the complex’s site lighting, replacing outdated, inefficient fixtures with modern LED lighting to improve energy efficiency, visibility, and safety across the campus. Across all projects, we conducted field investigations to assess existing building systems and ensure our designs integrated smoothly with the facility’s central infrastructure. Special attention was given to coordinating each renovation with the hospital’s existing utility systems to ensure continuity of operations and minimize disruption in an occupied healthcare environment. The upgrades focused on supporting specialized equipment needs, improving ventilation and comfort for patients and staff, and meeting healthcare-specific standards for safety, lighting, and hygiene.

Results

These renovations provided much-needed upgrades to aging infrastructure while expanding the center’s ability to serve the community. Each space was modernized to support current clinical workflows, improve energy efficiency, and enhance the overall patient experience—from brighter, more comfortable treatment areas to improved air quality and staff support zones.

Scope of Services
Mechanical, Electrical, Plumbing, and Fire Protection (MEP/FP) Engineering
 

OWNER: UVA Health

TIMEFRAME: 2020 – 2023

SIZE: Varies

COST: ~$80,000


Highlights

System Highlights

Main Hospital

Mechanical

  • Modified and extended existing hot water VAV systems for infusion bays and pre-op unit
  • Installed new terminal units and ductwork to support reconfigured clinical zones
  • Added exhaust fan for isolation bay and adjusted RTU ductwork and makeup air for café renovation
  • Coordinated all upgrades with central plant and existing infrastructure

Electrical

  • Reconfigured power and lighting for clinical and dining areas
  • Installed LED lighting with integrated controls and nurse call coordination
  • Updated fire alarm devices to match new layouts

Plumbing

  • Extended domestic water, sanitary, and vent piping for sinks and medical equipment
  • Provided medical gas for pre-op bays and grease waste for café kitchen
  • Coordinated tie-ins to existing infrastructure in occupied areas

 

OBGYN Clinic

Mechanical

  • Provided new split-system fan coil units and an outdoor air unit for space conditioning and ventilation
  • Extended ductwork and piping to support reconfigured clinic layout
  • Zoned systems to serve exam rooms, offices, and procedure areas for comfort and efficiency

Electrical

  • Installed LED lighting and updated controls throughout clinic
  • Reconfigured power systems to support medical equipment and staff workstations
  • Integrated fire alarm and life safety systems with building infrastructure

Plumbing

  • Installed domestic water and sanitary piping for sinks, toilets, and exam room fixtures
  • Provided point-of-use mixing valves and emergency eyewash fixtures
  • Consolidated and replaced rooftop gas service for HVAC and water heating systems