Timeframe

2012 – 2015

Size

266,000 SF

Cost

$61 million

2RW provided MEP/FP engineering for these two new high schools. Each school included a 690-ton chilled water plant that consists of a primary 390-ton variable speed helical rotary screw water-cooled chiller, a part-load 250-ton helical rotary screw water-cooled chiller, and a 50-ton dedicated heat recovery chiller.

Project Goals

Loudoun County Public Schools (LCPS) is Virginia’s fastest-growing school division and one of the fastest-growing school districts in the United States. LCPS participates in the Collaborative for High Performance Schools (CHPS), a leading a national movement to improve student performance and the educational experience by building the best possible schools. In so doing, it has distinguished itself as a provider of superior educational facilities. Riverside high school was one of several schools built to support the County’s rapidly-growing student population.

Services

2RW provided full MEP/FP design for the new school and athletic complex based on an LCPS school prototype design developed 15 years earlier.

As part of the MEP/FP design process, 2RW provided energy modeling services to verify that the school, when built, would meet the CHPS energy performance prerequisite of consuming 15% less site energy than a baseline building. 2RW also made recommendations for updating the building prototype to incorporate design and technology advancements, reduce capital expenses and operational costs, and meet energy performance requirements. Additional adjustments were made to simplify the building layout and fire separations and incorporate daylighting strategies for more natural light.

2RW also provided MEP/FP design for the school’s athletic complex which consisted of combined football and track-and-field facilities, baseball and softball fields, tennis courts, and related concessions, restrooms, utility buildings, and press boxes. Field lighting was carefully designed to accommodate field orientation, location, and illuminance to ensure uniform light distribution and minimize over-spill into surrounding neighborhoods.

Results

Energy models predicted a 25.7% reduction in energy consumption compared to a baseline. Factoring in prevailing utility rates this equates to a 20% cost savings, which exceeds the CHPS minimum energy performance requirement.

Partners

Loudoun County Public Schools

Urban LTD

Awards

2RW Logo
Team
Adrienne Hendrickson, PE, LEED AP BD+C | | 2RW

Adrienne Hendrickson, PE

Senior Electrical Engineer

Project Gallery