Scope of Services
Mechanical, Electrical, Plumbing, and Fire Protection (MEP/FP) Engineering
 

The natatorium was constructed in 1996 as a state-of-the-art facility. Over time, the harsh pool environment degraded the HVAC equipment until there was inadequate air circulation to remove chemical contaminants at the pool’s surface.

2RW Project Case Study Main Image
Services

2RW designed and implemented improvements to the natatorium environmental conditioning and pool water treatment systems to
Improve natatorium air quality, air distribution, air exchange rate, and outdoor air ventilation.

  • Enhance air handling equipment efficiency and reliability.
  • Reduce the cost of maintaining air handling equipment.
  • Simplify air handling equipment operation for the facility’s staff.

2RW also provided cost estimation and value management services at the completion of the pre-design process to help guide the University’s capital budget process.

Scope of Services
Mechanical, Electrical, Plumbing, and Fire Protection (MEP/FP) Engineering
 

OWNER: University of Virginia

TIMEFRAME: 2010 – 2012

SIZE: 32,000 SF

COST: $3.16 million


Highlights

This project was complicated by a restricted mechanical equipment room and the need for the facility to remain operational during the design, construction, and commissioning processes. 2RW worked closely with the University and contractor to develop a construction phasing plan that successfully constrained the natatorium closing to a six-week period. In the end,  the contractor completed work and brought new systems online ahead of schedule.