Gunston Middle School and Community Center is a joint-use facility that comprises a middle school and community space for Arlington County Department of Parks and Recreation. The 50-year old MEP systems had been updated and partially replaced several times over the past decade and were in need of modernization.
Under our term contract, and as the prime consultant on this project, 2RW’s services included:
The renovated systems are more energy-efficient and maintain temperature and humidity conditions in all seasons, making it more comfortable for students, teachers, staff, and community members.
OWNER: Arlington Public Schools
TIMEFRAME: 2017 – 2019
SIZE: 230,000 SF
COST: $8.75 million
Disruption to students and staff was kept to a minimum through careful planning and coordination of construction over two phases.